A scrum team plans in two-week cycles and wants a project field that automatically generates the current and upcoming time-boxed periods so items can be assigned to a cycle and burndown reported per cycle. Which custom field type should they add?
- A. Date
- B. Iteration✓ Correct
- C. Number
- D. Single select
Explanation
The iteration field type creates repeating, configurable time periods (with breaks if desired) and powers iteration-based grouping, filtering, and insights. Single select would require manually creating and maintaining an option for every sprint. A date field captures a single point in time, not a period. A number field stores numeric values such as estimates.